    Kenya Faces $339 Million Exit Bill to Unwind Cancelled Adani Power Line Contract
    Seen Kenya

    Kenya Faces $339 Million Exit Bill to Unwind Cancelled Adani Power Line Contract

    The Kenyan National Treasury estimates it could cost Sh43.94 billion to unwind Gautam Adani's cancelled power line deal with Ketraco. The termination payment exceeds the original construction cost of the infrastructure projects.

    SY

    SHAHID YAKUB

    November 24, 2026  ·  3 min read

    Kenya's National Treasury estimates that unwinding Indian billionaire Gautam Adani's cancelled power line deal could cost Sh43.94 billion, equivalent to $339 million. The termination payment linked to the contract between Adani Energy Solutions Ltd. and the state-owned Kenya Electricity Transmission Co., known as Ketraco, appears in the Treasury's fifth annual report on public-private partnerships covering the year to June 2026. President William Ruto ordered the contract scrapped two years prior, alongside a separate proposal for Adani to take over and expand Jomo Kenyatta International Airport. The move followed U.S. prosecutors indicting Gautam Adani over an alleged bribery scheme in India, which the Adani Group has denied.

    The 30-year deal was originally signed in October 2024 for Adani Energy Solutions to build, finance, and run power lines and substations. The wider agreement carried a valuation of Sh95.68 billion, or $739 million. The two specific power lines named in the termination estimate, which include the 400-kilovolt Lessos-Loosuk line and the 220-kilovolt Kisumu, or Kibos, to Kakamega-Musaga line, were expected to cost about Sh41 billion combined. This valuation means the estimated exit payment sits roughly Sh3 billion higher than the total cost of constructing the two lines themselves. Treasury's broader tally of termination payments across 12 public-private projects shows a maximum exposure of Sh400.34 billion.

    Despite the cancellation announcement during the State of the Nation address on November 21, 2024, the termination process remains ongoing. The formal unwinding began in the 2024-25 financial year and was still under way at the end of June 2026. Ketraco and the Public Private Partnerships Directorate are currently pursuing a mutual separation designed to settle verified costs that Adani incurred before the agreement was terminated. Treasury Cabinet Secretary John Mbadi informed lawmakers shortly after the cancellation that the agreement had been legally terminated, although the Treasury has directly linked the abandoned deal to a shortfall in expected private investment inflows.

    Why This Matters

    Contingent liabilities of this magnitude highlight the financial vulnerabilities states face when major infrastructure agreements unravel under sudden political or legal pressure. When a termination penalty exceeds the capital expenditure required to build the underlying assets, public balance sheets absorb an immediate fiscal shock without gaining any productive capacity. This dynamic complicates future negotiations for capital-constrained governments attempting to leverage private finance for critical energy transmission infrastructure.

    Public-private partnership frameworks across the continent rely heavily on predictable legal environments and stable counterparty relationships. Legal disputes, international indictments of foreign investors, and abrupt executive interventions introduce severe project execution risks that deter institutional capital. Managing these liabilities requires rigorous risk allocation models, transparent cost verification protocols, and cautious probability weightings to prevent contingent obligations from crowding out essential public expenditure.

    Opportunities

    • Contractors: Engagement in alternative procurement tenders once Ketraco re-advertises the construction of the Lessos-Loosuk and Kisumu-Kakamega-Musaga transmission lines.
    • Financiers: Advisory roles in auditing public-private partnership pipelines and applying World Bank probability methods to contingent liabilities.
    • Legal Experts: Advising state entities on structuring mutual separation agreements and verifying pre-termination expenditures.
    • Operators: Bidding for upcoming transmission concessions under revised regulatory frameworks that account for political and counterparty risk.